To start and stop easier the sequences we will add few Tasks:

  • Go to the Task tab and add a Task named Go Castle 1
  • Drag & drop the SHOW timeline into the Subtasks area
  • Select it and in the Editor select Grand Master 0 duration 2sec
  • Copy/Paste this subtask
  • Select the pasted subtask, add a delay time of 2 seconds and replace Grand Master by Play at 00:00:00:00
  • Copy/Paste this subtask and replace the Play at by Grand Master 100 duration 2sec (no delay)

  • Copy the Task and paste to duplicate
  • Rename it by “GO Castle 2” and change the Play at to 00:00:57:11

Repeat for Go Castle 3 with a Play at 00:01:41:20